Skip to content
Altaica Urban
Refused

Rue de la Mélopée 27

Molenbeek-Saint-Jean · 12/SFD/485053 · Permis d'urbanisme – saisine du fonctionnaire délégué

Rue de la Mélopée 27, Molenbeek-Saint-Jean: extension or raising. Case refusé, lodged on 25 March 2013. The decision was notified on 8 May 2013, 44 days after lodging. The project creates 51 m² of housing.

construire un troisième étage.
The application's own description, in its source language (FR). Source: Nova.
51
Housing floor area created
Key figures
Permit typePermis d'urbanisme – saisine du fonctionnaire délégué
StatusRefusé
Lodged on25 March 2013date the file was received
Decision notified8 May 201344 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Decision notified · Refused

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
26 mExtension or raisingla régularisation des volumes annexes arrières au RDC et R+1 et des modifications de la façade avant, ainsi que l’ajout 2024
33 mTree fellingAbattre un arbre à haute tige (bouleau)2024
33 mTree fellingAbattage d'un arbre à haute tige ( bouleau)2024
39 mExtension or raisingla surélévation d’un immeuble de rapport avec l’ajout d’un logement au R+3, la régularisation des modifications intérieu2023
44 mOthermodifier la zone de recul2025

Other nearby cases : 12/GOU_PU/2016931, 12/PU/1958358, 12/PU/1901122, 12/PFD/2001491, 12/PU/2019491, 12/PU/2021689, 12/PU/1897568, 12/SFD/1857554, 12/PU/1800049, 12/PU/1950339, 12/PU/1942181, 12/PU/2032857, 12/PU/1991974, 12/PU/1826024, 12/PU/1937191, 12/PU/2000869, 12/PU/1810647, 12/PU/1977605, 12/PFD/1980898, 12/SFD/2021901, 12/PU/1987184, 12/PU/1800653, 12/PU/1843228, 12/GOU_PU/1859781, 12/PU/1820386

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)