Skip to content
AltUrb
Granted

Rue de Moscou 29

Saint-Gilles · 13/IPE/1722476 · Permis d'environnement

Rue de Moscou 29, Saint-Gilles: —. Case octroyé, lodged on 13 August 2019. The decision was notified on 18 October 2019, 66 days after lodging.

047B4
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on13 August 2019date the file was received
Decision notified18 October 201966 days
Works started17 October 2019
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Works started
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
18 mExtension or raisingconstruire une buanderie au premier étage en lieu et place d’une terrasse couverte et d’un WC2023
18 mPublic spaceConstruire une enceinte étanche pour son remplacement . La machine à pieux devra se positionner aux droits de ces arbres2025
23 mTree fellingabattre un arbre à haute tige2023
28 mSplit into dwellingsaménager un studio dans les mansardes de l’immeuble avec travaux structurels2023
28 mSplit into dwellingscréer 2 logements en duplex aux niveaux supérieurs et inférieurs avec travaux structurels et démolition des wc aux entre2024

Other nearby cases : 13/PU/1900129, 13/PU/1833069, 13/GOU_PU/1843851, 13/PU/1837618, 13/PU/1800583, 13/PU/1799710, 13/PU/1864914, 13/PU/1907715, 13/PU/2013980, 13/PU/1981712, 13/PU/1871454, 13/PU/2038786, 13/PU/1829503, 13/PU/2004854, 13/PU/1948781, 13/PU/2016148, 13/GOU_PU/1981103, 13/PU/1966571, 13/PU/1833423, 13/PU/2003818, 13/PU/1799218, 13/PU/1916429, 13/PU/1934157, 13/PU/1914276, 13/GOU_PU/1864016