Skip to content
Altaica Urban
Granted

Place Maurice Van Meenen 39

Saint-Gilles · 13/IPEPLP/1749948 · Prolongation de PE

Place Maurice Van Meenen 39, Saint-Gilles: operation of installations. Case octroyé, lodged on 23 May 2020. The decision was notified on 10 January 2022, 597 days after lodging.

Exploitation de l'hôtel communal de Saint-Gilles
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on23 May 2020date the file was received
Decision notified10 January 2022597 days
Works started24 February 2022
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
67 mPublic spaceRequalifier et réaménager les abords de l’hôtel de ville de Saint-Gilles.2025
67 mHeavy renovationmodifier les aménagements intérieurs de la maison unifamiliale avec travaux structurels, le volume, la façade et aménage2025
80 mHeavy renovationrégulariser la réalisation de travaux structurels dans l’annexe arrière au rez-de-chaussée (modification du plancher)2026
80 mFaçade and windowsremplacer deux châssis en façade au 3e étage2024
83 mFaçade and windowsmodifier la façade (192)2024

Other nearby cases : 13/PU/1966600, 13/PU/1864598, 13/PU/1864842, 13/PFD/1962535, 13/PU/1821495, 13/PU/2006888, 13/PU/2040221, 13/PU/1821116, 13/PU/1867213, 13/PU/1810526, 13/PU/1977027, 13/PU/1966736, 13/PU/2005491, 13/PU/1948530, 13/PU/2033976, 13/PU/1898859, 13/PU/2010987, 13/PU/1897332, 13/PU/1910058, 13/PU/2031100, 13/PU/1847584, 13/PFD/1940759, 13/PU/1926559, 13/PU/1849345, 13/PU/1830282

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)