Rue de Hollande 49
Saint-Gilles · 13/PFD/1780969 · Permis d'urbanisme délivré par le FD
Rue de Hollande 49, Saint-Gilles: change of use. Case octroyé, lodged on 19 March 2021. The decision was notified on 9 December 2021, 265 days after lodging.
Transformer un ancien garage en centre pour jeunes (CuBe - centre urbain d'expression).| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 March 2021 | date the file was received |
| Decision notified | 9 December 2021 | 265 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Change of use | Transformer un ancien garage en centre pour jeunes (CuBe) - modifier l'isolation de la façade à rue au niveau +1. | 2022 |
| 15 m | Extension or raising | étendre le funérarium au sous-sol, effectuer des modifications structurelles, des aménagements intérieurs et extérieurs | 2022 |
| 16 m | Roof | Isoler le pignon latéral mitoyen gauche et la toiture, créer des terrasses arrière au 1er étage et modifier la façade av | 2025 |
| 33 m | New construction | régulariser la construction d’un cabanon en fond de parcelle | 2026 |
| 33 m | Tree felling | aménager une terrasse et un escalier extérieur | 2022 |
Other nearby cases : 13/PU/2030185, 13/PU/1954103, 13/PU/2021794, 13/PU/2010490, 13/PU/1979581, 13/PU/1994136, 13/PU/2011413, 13/PU/1950526, 13/PU/1939363, 13/GOU_PU/1935869, 13/PFD/1915270, 13/PU/1945329, 13/PU/1995998, 13/PU/2039666, 13/PU/1985003, 13/PU/1952074, 13/PU/1868281, 13/PU/2030598, 13/PU/1972072, 13/PU/1835780, 13/PU/1962131, 13/PU/1848706, 13/PU/2031466, 13/PU/1993192, 13/PU/1863870
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)