Granted
Place Bara
Saint-Gilles · 13/PFD/694309 · Permis d'urbanisme délivré par le FD
Place Bara, Saint-Gilles: public space. Case octroyé, lodged on 9 August 2018. The decision was notified on 17 August 2018, 8 days after lodging.
Abattre 16 arbres et en remplacer 14 dans différentes voiries régionales à Saint-Gilles| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 9 August 2018 | date the file was received |
| Decision notified | 17 August 2018 | 8 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.