Rue du Progrès 56
Saint-Josse-ten-Noode · 14/IPEEXT/1986752 · Extension / Transformation de PE
Rue du Progrès 56, Saint-Josse-ten-Noode: operation of installations. Case octroyé, lodged on 16 May 2025. The decision was notified on 27 May 2025, 11 days after lodging.
Modification de notre UPS| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 May 2025 | date the file was received |
| Decision notified | 27 May 2025 | 11 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 60 m | Change of use | Réaménager et changer la destination et l'utilisation des locaux situés passage Charles Rogier 23, à Saint-Josse-ten-Noo | 2024 |
| 60 m | Change of use | Transformer et rénover des cellules commerciales en des salles de réunions et une salle polyvalente; construire un parki | 2025 |
| 83 m | Signs and advertising | maintenir un planimètre de 2 m² (SJ1550) | 2022 |
| 83 m | Public space | Relocalisation temporaire des arrêts et zones d’attente des bus De Lijn et STIB pendant la construction du projet NOR (e | 2025 |
| 110 m | Retail or horeca fit-out | Installer une cheminée d'évacuation des fumées de la hotte du restaurant | 2026 |
Other nearby cases : 14/PU/2022669, 14/PU/1910506, 14/PFD/1924942, 14/PU/1829737, 14/PFD/1908297, 14/PU/1956639, 04/PFD/1811312, 14/PFU/1924346, 14/PFU/2036051, 14/PU/1856477, 14/PU/1849743, 14/PFD/1977252, 14/PU/2009991, 14/PU/1944045, 14/PU/1973018, 14/PU/2022017, 14/PFD/1977253, 14/PFD/1997041, 14/PFD/1909616, 14/GOU_PU/1924104, 14/PU/1908754, 14/PFD/1811303, 14/PFD/1977254, 14/PU/1800189, 14/PFD/1981207