Skip to content
AltUrb
Granted

Rue Scailquin 63

Saint-Josse-ten-Noode · 14/IPEPLP/601064 · Prolongation de PE

Rue Scailquin 63, Saint-Josse-ten-Noode: operation of installations. Case octroyé, lodged on 19 May 2016. The decision was notified on 12 May 2017, 358 days after lodging.

Installation de génération d'électricité
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on19 May 2016date the file was received
Decision notified12 May 2017358 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mMerger of dwellingsRelier un apprtement à 2 chambres de bonne en créant un escalier interne.2025
0 mChange of usetransformer un salon-lavoir en logement '(appartement 2 chambres)2023
40 mSigns and advertisingPlacer un panneau publicitaire de 17 m² sur un mur pignon2023
44 mEnergy worksmettre en conformité les installations techniques de désenfumage du parking Scailquin et le système de ventilation2024
45 mHeavy renovationRénover et transformer une maison unifamiliale en 3 logements2025

Other nearby cases : 14/PU/1894005, 14/PU/2005132, 14/PU/1904406, 14/PU/1908749, 14/PU/1834664, 14/PU/1969730, 14/PU/1855538, 14/PU/1934370, 14/PU/1870812, 14/PU/1856656, 14/PU/2029941, 14/PFU/2029466, 14/PU/1994584, 14/PU/1916995, 14/PU/1906816, 14/PU/1933898, 14/PU/1870944, 14/PU/1871767, 14/PFU/1955615, 14/PU/1941403, 14/PU/1898117, 14/PU/1823915, 14/PU/1913600, 14/PFD/1951663, 14/PU/1937422