Withdrawn

Boulevard Saint-Lazare

Saint-Josse-ten-Noode · 14/IPETMP/456030 · Permis d'environnement temporaire

Boulevard Saint-Lazare, Saint-Josse-ten-Noode: —. Case annulé, lodged on 15 December 2009. The decision was notified on 1 February 2010, 48 days after lodging.

Key figures
Permit typePermis d'environnement temporaire
StatusAnnulé
Lodged on15 December 2009date the file was received
Decision notified1 February 201048 days
Works started25 August 2011
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.