Rue des Deux Tours 99, Saint-Josse-ten-Noode: office conversion. Case octroyé, lodged on 18 February 2026. The decision was notified on 30 June 2026, 132 days after lodging.
réaffecter un bureau en logement| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 February 2026 | date the file was received |
| Decision notified | 30 June 2026 | 132 days |
| Floor areas | — | not reported by the source |
| Competent authority | Saint-Josse-ten-Noode |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 6 m | Heavy renovation | transformer un logement duplex au 4ème étage et créer deux lucarnes en façade avant et arrière | 2025 |
| 10 m | Change of use | mettre en conformité un ETABLISSEMENT D’HEBERGEMENT COLLECTIF avec 10 chambres (bâtiment principal), une SALLE POLYVALEN | 2024 |
| 42 m | Extension or raising | mettre en conformité la fermeture du balcon arrière au R+1 | 2025 |
| 42 m | Split into dwellings | transformer une maison unifamiliale et mettre en conformité l’extension arrière | 2026 |
| 52 m | Extension or raising | rehausser des annexes en façade arrière d'une maison unifamiliale | 2022 |
Other nearby cases : 14/PU/1988415, 14/PU/1976410, 14/PU/1962256, 14/PU/1997173, 14/PU/1860030, 14/PU/1986976, 14/PU/1901748, 14/PU/1982794, 14/PFU/2026809, 14/PFU/1961610, 14/PU/1846928, 14/PU/1957715, 14/PU/1820179, 14/PFU/1859772, 14/PFU/1831964, 14/PFU/1855469, 14/PU/2038376, 14/PU/1957640, 14/PU/2037052, 14/PFD/2003532, 14/PFD/1870403, 14/PFD/1980539, 14/PU/1853159, 14/PU/1846682, 14/PU/1917603
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)