Granted
Rue Colonel Bourg
Schaerbeek · 15/IPE/1844590 · Permis d'environnement
Rue Colonel Bourg, Schaerbeek: operation of installations. Case octroyé, lodged on 7 June 2022. The decision was notified on 4 November 2022, 150 days after lodging.
Exploitation d'une haute école| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 June 2022 | date the file was received |
| Public inquiry | 30 September 2022 – 15 October 2022 | |
| Decision notified | 4 November 2022 | 150 days |
| Works started | 17 February 2025 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 35 m | Change of use | dans un immeuble à usage mixte (une activité productive de biens immatériels et un logement), construire une annexe au r | 2025 |
| 69 m | Extension or raising | Rénover la cuisine, étendre le restaurant, rendre l'entrée accessible, connecter le bloc de construction A&B | 2022 |
| 112 m | Roof | Modifier le permis portant sur la construction du nouveau siège de la RTBF, référencé 15/PFD/1955071 et délivré le 21/02 | 2026 |
| 112 m | New construction | MEDIASQUARE II : Modifier le permis portant sur la construction du nouveau siège de la RTBF référencé 15/PFD/642903 et d | 2024 |
| 112 m | Roof | MEDIASQUARE IV : Diminuer l’emprise du volume du pavillon situé à l'avant droit en toiture (PERMIS MODIFICATIF « 3 » du | 2026 |
Other nearby cases : 15/PFD/2014644, 15/PU/1798974, 15/PFD/1846762, 15/PFD/2021909, 15/PFD/2038643, 15/PFD/2016276, 15/PFU/1988942, 15/PFD/1846381, 15/PFD/2014156, 15/PFD/1912113, 15/PU/1827168, 15/PU/2016674, 15/PFD/1956494
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)