Granted

Boulevard Général Wahis 18–20

Schaerbeek · 15/IPE/1957014 · Permis d'environnement

Boulevard Général Wahis 18–20, Schaerbeek: —. Case octroyé, lodged on 5 September 2024. The decision was notified on 2 December 2024, 88 days after lodging.

BX3471
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on5 September 2024date the file was received
Decision notified2 December 202488 days
Works started2 December 2024
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
70 mTree fellingAbattre trois cèdres et un tilleul dans le jardin de la copropriété 2026
125 mOtherRemplacement d'une structure imperméable gonflable par une structure ouvrable rigide couvrant deux terrains de tennis2025
125 mOtherConstruire une structure ouvrable rigide couvrant deux terrains de tennis et régulariser un terrain de mini-tennis const2025
167 mPublic spaceRéaménager la plaine de jeux "Cité Jardin" en ajoutant des chemins adaptés aux PMR, en créant différentes zones de jeux 2026
167 mTree fellingAbattre 20 arbres en mauvais état sanitaire et présentant un risque pour les biens et les personnes2023

Other nearby cases : 15/PFD/2002988, 15/AA/1848852, 15/PFD/2001266, 15/PU/1832820, 15/PU/1980176, 15/PU/1979338, 15/ECO/1832872, 15/PU/1849713, 15/PFD/1821930, 15/PU/1828907, 15/PU/1993942, 15/ENS/1929808, 15/PU/1954442, 15/PU/1943415, 15/PFD/1972217, 15/PU/2001795