Skip to content
AltUrb
Withdrawn

Boulevard Lambermont 236–238

Schaerbeek · 15/IPEEXT/488537 · Extension / Transformation de PE

Boulevard Lambermont 236–238, Schaerbeek: —. Case annulé, lodged on 11 June 2013. The decision was notified on 2 July 2013, 21 days after lodging.

Key figures
Permit typeExtension / Transformation de PE
StatusAnnulé
Lodged on11 June 2013date the file was received
Decision notified2 July 201321 days
Works started30 October 2013
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
60 mEnergy worksInstaller des carports couvrant 67 emplacements de parking surmontés de panneaux solaires.2023
60 mEnergy worksLe projet consiste en l’implantation de panneaux solaires sur une infrastructure au sol relevé par des structures portan2023
60 mNew constructionsur une parcelle non-bâtie, installer des "carports" couvrant 67 emplacements de parking surmontés de panneaux solaires 2023
65 mEnergy worksdans un immeuble de bureaux, placer 3 pompes à chaleur sur le sol, à coté du bâtiment2022
65 mNew constructionConstruire un abri pour une pompe à chaleur au rez-de-chaussée du bâtiment.2022

Other nearby cases : 15/AA/1821214, 15/PU/1826350, 15/PFD/1853901, 15/PU/1988680, 15/PU/1975585, 15/PU/1829233, 15/GOU_PU/1937100, 15/PFD/1838375, 15/PU/1856697, 15/PU/2020158, 15/PU/2015318, 15/PFD/1907848, 15/PU/1999658, 15/PU/2004605, 15/PU/2003965, 15/PU/1996137, 15/PU/1900431, 15/PU/1904025, 15/PU/1932891, 15/SFD/2019410, 15/PU/1993930, 15/PU/1897970, 15/PU/1837424, 15/PU/2038557, 15/PU/1969907

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)