Rue Colonel Bourg 114–116
Schaerbeek · 15/IPEPLP/1736787 · Prolongation de PE
Rue Colonel Bourg 114–116, Schaerbeek: operation of installations. Case octroyé, lodged on 24 December 2019. The decision was notified on 22 June 2020, 181 days after lodging.
Exploitation d'un immeuble de logements - Prolongation| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 December 2019 | date the file was received |
| Decision notified | 22 June 2020 | 181 days |
| Works started | 1 December 2020 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 5 m | Tree felling | abattre un peuplier dans le jardin de la copropriété | 2026 |
| 70 m | Regularisation | Mettre en conformité les modifications apportées au PU2015-116-10 | 2024 |
| 70 m | Regularisation | mettre en conformité les modifications réalisées. | 2022 |
| 70 m | Office conversion | Modifier le permis référencé 15/PFD/1781741, délivré le 19/07/2022 (Rénovation et extension d'un immeuble de bureau exis | 2024 |
| 95 m | Office conversion | Transformer un immeuble de bureaux en un ensemble de 34 logements avec 41 emplacements de parking. | 2023 |
Other nearby cases : 06/PFD/2019752, 15/PFD/1846762, 15/PFD/2016276, 15/PFD/2038643, 15/PFU/1988942, 06/PFD/1990521, 06/PFD/1974250, 15/PFD/2021909, 18/PFD/1820155, 15/PU/1798965, 15/GOU_PU/1829152, 06/PU/1838724, 06/PU/2003943, 06/SFD/1830915, 06/PU/1800689, 18/PU/1995439, 18/PU/2034590, 18/PU/1942229, 06/PU/2010325, 06/PU/2037890, 06/PU/2014398, 18/PU/1832809, 15/AA/1837315