Skip to content
AltUrb
Withdrawn

Rue de Jérusalem 56

Schaerbeek · 15/IPETMP/455149 · Permis d'environnement temporaire

Rue de Jérusalem 56, Schaerbeek: —. Case annulé, lodged on 15 June 2009. The decision was notified on 8 July 2009, 23 days after lodging.

Key figures
Permit typePermis d'environnement temporaire
StatusAnnulé
Lodged on15 June 2009date the file was received
Decision notified8 July 200923 days
Works started30 July 2009
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
68 mChange of usesur une parcelle composée d’un bâtiment avant (entrée gauche au n°44) affecté à 3 logements et d’un bâtiment arrière (en2024
68 mChange of useChanger l'affectation d’un grand commerce spécialisé en commerce (parking de 30 emplacements au total).2024
78 mDemolitionsur deux parcelles comprenant des bâtiments affectés au commerce (y compris un parking extérieur de 19 places), démolir 2022
93 mExtension or raisingdans un immeuble comprenant un commerce au rez-de-chaussée, rehausser l'immeuble de 4 étages, construire une annexe arri2022
93 mExtension or raisingDans un immeuble comprenant 1 commerce : - rehausser l’immeuble et aménager 3 logements, - créer une annexe semi-ent2021

Other nearby cases : 15/PU/1912993, 15/PU/1951357, 15/PU/1843335, 15/PFU/1950964, 15/PU/1958726, 15/PU/2027496, 15/PFD/1952747, 15/PU/1951115, 15/PFD/1958258, 15/PU/2034985, 15/PU/2036672, 15/PU/1892644, 15/GOU_PU/1935879, 15/PU/1912523, 15/PU/1932602, 15/PU/2032710, 15/PU/1962247, 15/PU/2022071, 15/PU/1835794, 04/PU/1849374, 15/PU/2038486, 15/PU/1907718, 15/PU/2021533, 15/PU/1934156, 15/PU/1952553

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)