Withdrawn

Square Apollo 1

Schaerbeek · 15/IPETMP/613228 · Permis d'environnement temporaire

Square Apollo 1, Schaerbeek: operation of installations. Case annulé, lodged on 12 October 2016. The decision was notified on 22 December 2016, 71 days after lodging.

Asbestwerf
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'environnement temporaire
StatusAnnulé
Lodged on12 October 2016date the file was received
Decision notified22 December 201671 days
Works started16 January 2017
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Withdrawn
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.