Rue Colonel Bourg 103

Schaerbeek · 15/IPETMP/658344 · Permis d'environnement temporaire

Rue Colonel Bourg 103, Schaerbeek: operation of installations. Case annulé, lodged on 30 November 2017. The decision was notified on 1 February 2018, 63 days after lodging.

asbestwerf
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'environnement temporaire
StatusAnnulé
Lodged on30 November 2017date the file was received
Decision notified1 February 201863 days
Works started16 April 2018
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Withdrawn
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mOffice conversionTransformer un immeuble de bureaux en un ensemble de 34 logements avec 41 emplacements de parking.2023
47 mOffice conversionModifier le permis référencé 15/PFD/1781741, délivré le 19/07/2022 (Rénovation et extension d'un immeuble de bureau exis2024
57 mDemolition and reconstructiondémolir la partie hors-sol d'un immeuble de bureaux, transformer les sous-sols et construire un bâtiment comprenant 64 a2022
93 mTree fellingabattre un peuplier dans le jardin de la copropriété2026
94 mRegularisationmettre en conformité les modifications réalisées.2022

Other nearby cases : 06/PU/1941343, 06/PFD/2019752, 18/PU/1995439, 18/PU/2034590, 15/AA/1837315, 18/PU/1832809, 18/PU/1865907, 15/PFD/2016276, 15/PFD/2038643, 15/PFU/1988942, 18/PU/2002069, 18/PU/1945553, 18/PU/1942229, 15/PU/2002407, 15/PFD/2021909, 06/PFD/1974250, 06/PFD/1990521, 18/PFD/1820155, 18/AA/1799735, 18/PU/1905193, 18/PU/1897813