Granted
Rue Gaucheret
Schaerbeek · 15/PFD/119172-01 · Permis d'urbanisme délivré par le FD
Rue Gaucheret, Schaerbeek: new construction. Case octroyé, lodged on 7 September 1998. The decision was notified on 19 January 1999, 134 days after lodging.
Installer un pavillon préfabriqué| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 September 1998 | date the file was received |
| Decision notified | 19 January 1999 | 134 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)