Granted
Rue du Progrès
Schaerbeek · 15/PFD/155166 · Permis d'urbanisme délivré par le FD
Rue du Progrès, Schaerbeek: new construction. Case octroyé, lodged on 16 March 2004. The decision was notified on 15 July 2004, 121 days after lodging.
bouwen van een hoogspanningspost| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 March 2004 | date the file was received |
| Decision notified | 15 July 2004 | 121 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.