Refused
Place Colignon
Schaerbeek · 15/PFU/164453 · Permis d'urbanisme unique délivré par le FD
Place Colignon, Schaerbeek: façade and windows. Case refusé, lodged on 4 July 2005. The decision was notified on 20 January 2006, 200 days after lodging.
remplacer les 2 doubles portes en verre du sas du hall d'entrée de l'Hôtel communal| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Refusé | |
| Lodged on | 4 July 2005 | date the file was received |
| Consultation committee | 14 October 2005 | |
| Decision notified | 20 January 2006 | 200 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Refused
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)