Skip to content
AltUrb
Granted

Rue du Noyer 282–282b

Schaerbeek · 15/PFU/1990035 · Permis d'urbanisme unique délivré par le FD

Rue du Noyer 282–282b, Schaerbeek: façade and windows. Case octroyé, lodged on 10 June 2025. The decision was notified on 18 August 2025, 69 days after lodging.

Placer un double vitrage dans des menuiseries extérieures classées.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on10 June 2025date the file was received
Decision notified18 August 202569 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mSplit into dwellingsRégulariser 2 unités de logement au sein d'une copropriété (au lieu de 1 unité de logement stipulé dans la situation de 2022
0 mOtherPlacer une protection réversible contre les pigeons sur les balcons des façades intérieures des blocs 1 et 22023
0 m15/PU/18327312022
31 mFaçade and windowsPlacer un double vitrage dans des menuiseries extérieures classées.2025
44 mRoofprocéder à la couverture de deux sorties de secours d'un garage situé à l'arrière du bâtiment principal2026

Other nearby cases : 15/PU/2020707, 04/PU/1821933, 04/PU/1866250, 04/PU/1837277, 15/PU/1984466, 15/PFD/1984355, 15/PFD/1959573, 15/GOU_PU/1966863, 15/PU/1912755, 15/SFD/1826202, 04/PU/1990854, 15/PU/2004810, 15/PU/1938664, 15/PU/2028698, 04/PU/1908600, 15/PU/1959484, 15/PU/1994146, 15/PU/1995283, 04/PU/1913451, 04/PFU/1849086, 15/PU/2006847, 04/PU/2031464, 15/PU/2042277, 15/ENS/2004525, 15/PU/2012858

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)