Skip to content
AltUrb
Granted

Place Colignon

Schaerbeek · 15/PFU/282104 · Permis d'urbanisme unique délivré par le FD

Place Colignon, Schaerbeek: roof. Case octroyé, lodged on 6 May 2010. The decision was notified on 7 December 2010, 215 days after lodging.

Aménager des bureaux dans les combles de l'Hôtel Communal.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on6 May 2010date the file was received
Consultation committee29 October 2010
Decision notified7 December 2010215 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Consultation committee
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)