Granted
Avenue du Suffrage Universel
Schaerbeek · 15/PFU/408380 · Permis d'urbanisme unique délivré par le FD
Avenue du Suffrage Universel, Schaerbeek: public space. Case octroyé, lodged on 22 November 2011. The decision was notified on 20 December 2011, 28 days after lodging.
Installer le chantier pour la rénovation des abords du stade du Crossing| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 22 November 2011 | date the file was received |
| Decision notified | 20 December 2011 | 28 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)