Skip to content
AltUrb
Granted

Avenue Milcamps 67

Schaerbeek · 15/PU/1850801 · Permis d'urbanisme privé

Avenue Milcamps 67, Schaerbeek: heavy renovation. Case octroyé, lodged on 1 August 2022. The decision was notified on 14 September 2023, 409 days after lodging. The project creates 12 m² of housing.

REALISE : dans une maison unifamiliale, construire un escalier extérieur, effectuer des travaux structurels intérieurs et apporter des modifications en façade avant
The application's own description, in its source language (FR). Source: Nova.
12
Housing floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 August 2022date the file was received
Public inquiry26 May 2023 – 10 June 2023
Consultation committee22 June 2023
Decision notified14 September 2023409 days
Works started16 October 2023
Competent authoritySchaerbeek

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted
  8. Works started
  9. event_works_ended

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingREALISE : dans une maison unifamiliale, mettre en conformité la construction d'une annexe au 3ème étage, ajouter une luc2023
7 mTree fellingabattre un frêne dans le jardin2024
7 mTree fellingabattre un frêne dans le jardin2023
30 mExtension or raisingREALISE : dans un immeuble comprenant deux logements et un emplacement de parking, mettre en conformité l’extension du l2022
31 mSplit into dwellingsDiviser une maison unifamiliale en 4 logements (passer de 1 à 3 unités) et réaliser des travaux structurels2026

Other nearby cases : 15/GOU_PU/2004485, 15/PU/1948151, 15/PU/2039845, 15/PU/1979072, 15/PU/1827221, 15/PU/1828520, 15/PU/1906783, 15/PU/1990495, 15/PU/2008251, 15/PU/1858478, 15/GOU_PU/1932060, 15/PU/1968901, 15/PU/1958244, 15/PFD/2026027, 15/PU/2004519, 15/PU/2008944, 15/ENS/1896605, 15/PU/1823305, 15/PU/1821569, 15/PU/2005034, 15/PU/1820245, 15/PU/1923316, 15/PU/2027225, 15/PFD/1946974, 15/PU/1861989

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)