Granted
Rue du Bourdon
Uccle · 16/CPFD/146754 · Certificat d'urbanisme délivré par le FD
Rue du Bourdon, Uccle: public space. Case octroyé, lodged on 6 January 2003. The decision was notified on 27 April 2007, 1 572 days after lodging.
mise à 4 voies de la ligne 124 entre la rue Bigarreaux et la limite régionale et création d'un point d'arrêt au croisement avec la ligne 26.| Permit type | Certificat d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 6 January 2003 | date the file was received |
| Consultation committee | 23 February 2005 | |
| Decision notified | 27 April 2007 | 1 572 days |
| Floor areas | — | not reported by the source |
| Impact study | yes | |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)