Granted
Rue Jean Ballegeer 69
Uccle · 16/IPE/1719021 · Permis d'environnement
Rue Jean Ballegeer 69, Uccle: —. Case octroyé, lodged on 9 July 2019. The decision was notified on 5 September 2019, 58 days after lodging.
02MIR| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 9 July 2019 | date the file was received |
| Decision notified | 5 September 2019 | 58 days |
| Works started | 4 September 2019 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Works started
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 40 m | Tree felling | Couper 12 arbres en état critique, ou en bonne santé | 2023 |
| 155 m | Tree felling | Couper 6 nouveaux arbres en état critique par rapport au permis initial. | 2023 |
| 158 m | Tree felling | abattre 2 arbres | 2023 |
| 158 m | Roof | aménager une terrasse pour l’appartement de 2 chambres (LOT n°26) prévus aux plans du PU (réf. 16/PFD/135923) de 2001, a | 2025 |
| 182 m | Extension or raising | mettre en conformité une cour couverte de 10m² remplacée par un volume bâti entre le volume principal de l'habitation et | 2025 |
Other nearby cases : 16/AA/1938741, 16/PFD/1840696, 16/PFD/1998995, 16/PU/2023778, 16/AA/1821150, 16/PU/1835672, 16/SFD/1851771, 16/LPFD/2022548, 16/PU/1971276, 16/SFD/1996541, 16/PU/1948922, 16/PFD/1827884