Skip to content
AltUrb
Withdrawn

Chaussée d'Alsemberg 1091

Uccle · 16/IPE/454919 · Permis d'environnement

Chaussée d'Alsemberg 1091, Uccle: —. Case annulé, lodged on 7 May 2009. The decision was notified on 26 January 2010, 264 days after lodging.

Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on7 May 2009date the file was received
Public inquiry26 October 2009 – 27 October 2009
Decision notified26 January 2010264 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mTree fellingAbattre 5 arbres morts ou dépérissants, dangereusement inclinés au-dessus d'un garage et d'une voie d'évacuation2025
112 mNew constructionConstruire 59 logements sociaux sur un terrain longeant la chaussée d'Alsemberg sous la forme de 4 immeubles avec un par2023
112 mNew constructionConstruire 59 logements sociaux sur un terrain longeant la chaussée d'Alsemberg sous la forme de 4 immeubles avec un par2025
112 mNew constructionConstruire 59 logements sociaux sur un terrain longeant la chaussée d'Alsemberg sous la forme de 4 immeubles avec un par2023
149 mTree fellingAbattage d'un marronnier2022

Other nearby cases : 16/PU/1943332, 16/PU/1858131, 16/PU/2022724, 16/PU/1837727, 16/PU/1826540, 16/GOU_PU/1849004, 16/PFU/2031588, 16/AA/1904745, 16/AA/1910449, 16/PU/1824895, 16/PU/1970970, 16/PU/1859857, 16/PU/1924930, 16/PU/1981227, 16/PFD/1834271, 16/PU/1978015, 16/PU/1843198, 16/PU/1937345, 16/PU/1997330, 16/PU/2004929, 16/PU/1967891, 16/PU/2002240

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)