Granted
Moensberg 2–24
Uccle · 16/IPE/458799 · Permis d'environnement
Moensberg 2–24, Uccle: —. Case octroyé, lodged on 29 June 2011. The decision was notified on 3 October 2011, 96 days after lodging.
| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 29 June 2011 | date the file was received |
| Decision notified | 3 October 2011 | 96 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 47 m | New construction | construire un immeuble de rapport composé de deux logements, un duplex et un simplex | 2023 |
| 47 m | New construction | MISE SANS SUITE : construire un petit immeuble de rapport de deux logements permis modificatif du PU 16-4699-2023 | 2023 |
| 58 m | Tree felling | abattre deux sapins | 2023 |
| 104 m | Extension or raising | isoler les façades extérieures et créer un garage annexé à la maison | 2023 |
| 108 m | Tree felling | Abattre 4 arbres | 2024 |
Other nearby cases : 16/PU/1918636, 16/PU/2027205, 16/PU/1940129, 16/PU/1976486, 16/PU/1824940, 16/PU/1849280, 16/PU/1828642, 16/AA/1928456, 16/AA/1976415, 16/PFD/1849803, 16/PU/1839691, 16/GOU_PU/1799891, 16/PU/1924921, 16/PU/2031071, 16/PU/2017080
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)