Rue Egide Van Ophem 110
Uccle · 16/IPEEXT/2037820 · Extension / Transformation de PE
Rue Egide Van Ophem 110, Uccle: operation of installations. Case octroyé, lodged on 3 July 2026. The decision was notified on 28 July 2026, 25 days after lodging.
correctie in beslissing m.b.t. warmtepompen| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 July 2026 | date the file was received |
| Decision notified | 28 July 2026 | 25 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 5 m | Other | Huidige aanvraag betreft een wijzigingsaanvraag van de reeds eerder verkregen stedenbouwkundige vergunning met referenti | 2025 |
| 5 m | Roof | Demande de modification de permis 102/1 : Modifier les matériaux de façade, la position des parties ouvrantes des fenêtr | 2025 |
| 38 m | Tree felling | Abattre un arbre | 2025 |
| 40 m | Other | Aanvraag wijzigingsvergunning voor dossier 16/PFD/1786113. | 2024 |
| 44 m | Change of use | De aanvraag betreft een wijziging van een appartement naar een medisch cabinet voor een tandartsenpraktijk ter hoogte va | 2026 |
Other nearby cases : 16/PU/2042635, 16/PFD/2036598, 16/PU/2036268, 16/AA/2012360, 16/PU/1968100, 16/PFD/1832917, 16/GOU_PU/1867063, 16/PFD/1825414, 16/PU/1956358, 16/AA/1863428, 16/AA/1950630, 16/PU/1907775, 16/PU/1825675, 16/PU/2034962, 16/PU/2023235, 16/PU/1973006, 16/PU/1996486, 16/PFD/1968742, 16/PFD/1832052, 16/AA/1830092, 16/PFD/1992570, 16/AA/1852601, 16/PU/1855929, 16/PU/2021467, 16/PU/1841696
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)