Skip to content
AltUrb
Withdrawn

Chaussée de Waterloo 935

Uccle · 16/IPEEXT/695929 · Extension / Transformation de PE

Chaussée de Waterloo 935, Uccle: energy works. Case annulé, lodged on 23 August 2018. The decision was notified on 20 September 2018, 28 days after lodging.

remplacement des chaudières
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusAnnulé
Lodged on23 August 2018date the file was received
Decision notified20 September 201828 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mRoofisoler toutes les toitures plates du bâtiment, installer des panneaux photovoltaïques sur deux toitures (A et E), végéta2023
39 mChange of usemodifier structurellement et agrandir un bâtiment existant, modifier la destination d'entrepôt vers une affectation comm2024
45 mSigns and advertisingplaatsen van een bannerframe met doel voor publiciteit2021
51 mOffice conversionmettre en conformité une situation de fait datant de la construction de l’immeuble et aménager un logement dans l’espace2025
71 mHeavy renovationverbouwing afdeling B3 RVT Nazareth2021

Other nearby cases : 16/PU/1902768, 16/PU/1957626, 16/SFD/1945562, 16/PU/1897857, 16/PU/1843596, 16/PU/1983858, 16/PU/1958670, 16/PFU/1841537, 16/AA/1820050, 16/PU/1945472, 16/SFD/1969544, 16/PU/1847124, 16/PU/2015549, 16/PFU/2015433, 16/PU/1828946, 16/PU/1849388, 16/PU/1954396, 16/PU/1924222, 16/PU/1977422, 16/AA/1894680, 16/PU/1962314, 16/PU/2029679, 16/PU/1990043, 16/AA/2016424, 16/AA/1868879