Granted

Chaussée d'Alsemberg 876

Uccle · 16/IPEPLP/1713770 · Prolongation de PE

Chaussée d'Alsemberg 876, Uccle: operation of installations. Case octroyé, lodged on 16 May 2019. The decision was notified on 11 June 2020, 392 days after lodging.

Exploitation d'une carrosserie et d'un atelier de réparation et d'entretien de véhicules automobiles
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on16 May 2019date the file was received
Decision notified11 June 2020392 days
Works started20 May 2020
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Works started
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
40 mExtension or raisingmodifier l’aménagement intérieur des appartements, réaménager le hall commun, construire un balcon au 2ème étage en faça2025
40 mSplit into dwellingsaménager un appartement dans les combles d’un immeuble de rapport2026
40 mFaçade and windowsdéplacer à front de rue une porte de garage2025
44 mRegularisationRégulariser le permis d'urbanisme PU 16-PFD-638633 du 18/08/2017 suite au PV d'infraction 16/INFS/6854652021
67 mRoofisoler la toiture d'une maison unifamiliale2022

Other nearby cases : 16/AA/1869652, 16/PU/1923294, 16/PU/1969067, 16/PFD/1968693, 16/PU/2042373, 16/PFD/2040868, 16/PU/1852507, 16/PU/1870695, 16/PU/1969227, 16/PU/1848607, 16/PU/1896838, 16/PU/2035273, 16/GOU_PU/1988917, 16/PU/1949330, 16/SFD/1997911, 16/PU/1957304, 16/PU/2043683, 16/PU/1846456, 16/PU/1853499, 16/PU/1911132, 16/GOU_PU/1851208, 16/PU/1823463, 16/PU/1961253, 16/PU/1941251, 16/PU/1945572

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)