Avenue du Prince de Ligne 83–95, Uccle: operation of installations. Case octroyé, lodged on 4 July 2025. The decision was notified on 20 February 2026, 231 days after lodging.

Prolongation du permis pour l'exploitation d'un parking en sous-sol (103 places).
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on4 July 2025date the file was received
Decision notified20 February 2026231 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
5 mEnergy worksposer une tente solaire en façade avant2022
5 mOtherinstaller un store solaire sur la terrasse du jardin. 2024
5 mEnergy worksposer une tente solaire2025
56 mTree fellingAbattre un arbre2024
60 mExtension or raisingconstruire une annexe en zone de retrait latéral2023

Other nearby cases : 16/AA/1970266, 16/AA/1799882, 16/AA/1931151, 16/PU/1982061, 16/PU/1871515, 16/AA/1903725, 16/PU/1827621, 16/PU/2015092, 16/AA/1952315, 16/AA/1866068, 16/AA/1864829, 16/PU/1866453, 16/PU/1983025, 16/PU/1978255, 16/PU/1827020, 16/GOU_PU/1851900, 16/PU/1967506, 16/PU/1974711, 16/PU/1843324, 16/PU/1948408, 16/PU/1991760, 16/PU/1959362, 16/PU/1993651, 16/AA/1850864, 16/AA/1978303

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)