Skip to content
Altaica Urban
Granted

Avenue de la Ferme Rose 8–10

Uccle · 16/IPEPLP/649653 · Prolongation de PE

Avenue de la Ferme Rose 8–10, Uccle: operation of installations. Case octroyé, lodged on 25 August 2017. The decision was notified on 18 June 2018, 297 days after lodging.

Immeuble de logements
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on25 August 2017date the file was received
Decision notified18 June 2018297 days
Works started26 August 2018
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mFaçade and windowsremplacer les garde-corps et les cloisons séparatrices des balcons au niveau des terrasses extérieures des 3 bâtiments, 2024
0 mRegularisationrégulariser l'appartement penthouse de l'immeuble n°10 suivant l'application de l'article 330 du CoBAT2025
0 mRoofmodifier les garde-corps des terrasses et balcons et réfectionner les façades et toitures2025
64 mTree fellingAbattre un thuya et un mirabellier2025
101 mFaçade and windowsmettre en conformité le remplacement des châssis par des menuiseries en PVC (teinte alu naturel) au rez-de-chaussée gauc2024

Other nearby cases : 16/AA/1973729, 16/AA/1988149, 16/PU/2023745, 16/PFD/2027891, 16/PU/2019674, 16/PU/1961361, 16/AA/2022884, 16/AA/1855116, 16/PU/2000395, 16/AA/2020070, 16/PU/1849072, 16/PU/1866612, 16/AA/1959613, 16/PU/1858987, 16/PU/1799121