Granted
Rue des Polders 1–36
Uccle · 16/PFD/224790 · Permis d'urbanisme délivré par le FD
Rue des Polders 1–36, Uccle: new construction. Case octroyé, lodged on 26 March 2009. The decision was notified on 4 November 2009, 223 days after lodging. The project creates 4 327 m² of housing. It comprises 40 dwellings.
Construire un immeuble de 40 appartements4 327m²
Housing floor area created
40
Dwellings created
| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 26 March 2009 | date the file was received |
| Public inquiry | 25 May 2009 – 9 June 2009 | |
| Consultation committee | 24 June 2009 | |
| Decision notified | 4 November 2009 | 223 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)