Granted
Chemin du Réservoir 1
Uccle · 16/PFU/1792688 · Permis d'urbanisme unique délivré par le FD
Chemin du Réservoir 1, Uccle: energy works. Case octroyé, lodged on 7 July 2021. The decision was notified on 12 April 2022, 279 days after lodging.
Placer 264 panneaux photovoltaïques sur la couverture d'un réservoir enterré d'eau potable de VIVAQUA.| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 July 2021 | date the file was received |
| Public inquiry | 24 January 2022 – 8 February 2022 | |
| Consultation committee | 23 February 2022 | |
| Decision notified | 12 April 2022 | 279 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Other | Remplacer une conduite de type Socarex de faible diamètre entre deux pavillons existants. Mise en œuvre de l'étanchéité | 2023 |
| 1 m | Other | Aménager deux terrains de padel sur le site du Réservoir de Boitsfort. | 2024 |
| 228 m | Public space | Remettre en état la drève où l’asphalte est le plus dégradé. | 2023 |
| 237 m | Other | Poser une armoire de matériel de télécommunication. | 2023 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)