Granted
Rue François Vervloet 179
Uccle · 16/PU/1699601 · Permis d'urbanisme privé
Rue François Vervloet 179, Uccle: regularisation. Case octroyé, lodged on 16 January 2019. The decision was notified on 6 May 2019, 110 days after lodging. The project creates 120 m² of housing.
mettre en conformité l'appartement duplex situé au 4ème étage et 5ème étage du bâtiment120m²
Housing floor area created
| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 January 2019 | date the file was received |
| Decision notified | 6 May 2019 | 110 days |
| Competent authority | Uccle |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Heavy renovation | Rénover un appartement 2 chambres Démolir un mur porteur séparant le séjour et la cuisine Pas de modification de la PE | 2022 |
| 95 m | Tree felling | mettre en conformité l'aménagement des abords de la maison et installer un portail le long de la rue des Trois Rois | 2026 |
| 96 m | New construction | Construire 37 appartements sociaux et moyens, répartis dans trois villas urbaines en rez+4 situées le long de la rue Fra | 2022 |
| 96 m | New construction | Construire 37 appartements sociaux et moyens, répartis dans trois villas urbaines en rez+4 situées le long de la rue Fra | 2022 |
| 96 m | New construction | Construire 37 appartements sociaux et moyens, répartis dans trois villas urbaines en rez+4 situées le long de la rue Fra | 2023 |
Other nearby cases : 16/PFD/1904389, 16/PFD/1839832, 16/PU/1849845, 16/PU/2026395, 16/AA/1835061, 16/PU/2005599
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)