Boulevard du Souverain 36
Watermael-Boitsfort · 17/IPE/1696996 · Permis d'environnement
Boulevard du Souverain 36, Watermael-Boitsfort: operation of installations. Case refusé, lodged on 13 December 2018.
immeuble de bureaux| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Refusé | |
| Lodged on | 13 December 2018 | date the file was received |
| Public inquiry | 6 May 2019 – 21 May 2019 | |
| Consultation committee | 13 June 2019 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Office conversion | Rénover lourdement un immeuble de bureaux vers un immeuble à affectations mixte : des espaces bureaux au rez (partiellem | 2024 |
| 75 m | Tree felling | abattre un arbre ,bouleau d'une hauteur d'environ 20 m et diamètre à ,1m50 du sol de 165 cm | 2022 |
| 90 m | Change of use | Transformer un immeuble de bureaux, avec un changement d'affectation partielle pour y installer un centre culturel ; rén | 2025 |
| 113 m | Extension or raising | étendre l'habitation | 2022 |
| 113 m | Extension or raising | agrandir et transformer une maison unifamiliale en immeuble de 3 appartements | 2024 |
Other nearby cases : 17/PU/1855207, 17/PU/1910769, 17/PU/1927337, 17/PU/1996881, 17/PU/2015228, 17/PU/1941514, 17/PU/1999600, 17/PU/2009841, 17/PU/2017086, 17/PU/1854404, 17/PU/1835722, 17/PU/1966812, 17/PU/1839831, 17/PU/1915793, 17/PU/1938608, 17/PFD/1837671, 17/PU/1999641, 17/PU/2042002, 17/PFU/1998123, 17/PU/2015207, 17/PFU/1933141, 17/PFU/1990850, 17/PFU/1927334, 17/PFU/1956469, 17/PFU/1832024
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)