Avenue du Col-Vert 1

Watermael-Boitsfort · 17/IPE/456612 · Permis d'environnement

Avenue du Col-Vert 1, Watermael-Boitsfort: operation of installations. Case annulé, lodged on 26 April 2010. The decision was notified on 23 September 2010, 150 days after lodging.

40.A système de chauffage 464 kW, 68.B parking couvert 48 places, 132.A Installation de refroidissement 518 kW, 148.A cabine haute tension 500 kVA, 153.A Ventilateurs 27000 m³/h
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on26 April 2010date the file was received
Public inquiry6 July 2010 – 7 July 2010
Consultation committee26 August 2010
Decision notified23 September 2010150 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
52 mMerger of dwellingsrégulariser la réunion de deux appartements2026
52 mFaçade and windowsinstaller une enseigne publicitaire lumineuse et remplacer le mur à l'extrême gauche de la façade avant par un nouveau m2024
52 mHeavy renovationrégulariser la réalisation de 2 box de garage fermés à partir des trois emplacements de stationnement d'origine dans le 2024
52 mTree fellingabattre 11 bouleaux arrivant en fin de vie et replanter des nouveaux arbres dans la même zone2026
53 mChange of usechanger la destination d'un bureau en un logement2023

Other nearby cases : 17/PU/1988561, 17/PU/1835741, 17/PFD/1963563, 17/PU/1951911, 17/PU/1932294, 17/PU/1932290, 17/PU/1978154, 17/PU/1995062, 17/PU/1841113, 17/PU/1824502, 17/PU/1980215, 17/PU/1801262, 17/PU/1801272, 17/PU/1801265, 17/PU/1801271, 17/PU/1980858, 17/PU/2034288, 17/PFD/1964915, 17/PU/1954157, 17/PU/1951989, 17/PU/1947119, 17/PU/1921821, 17/PU/1894334, 17/PU/2002329, 17/PU/1973423

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)