Skip to content
Altaica Urban
Granted

Boulevard du Souverain 23–25

Watermael-Boitsfort · 17/IPEEXT/1745502 · Extension / Transformation de PE

Boulevard du Souverain 23–25, Watermael-Boitsfort: operation of installations. Case octroyé, lodged on 20 March 2020. The decision was notified on 23 April 2020, 34 days after lodging.

wijziging
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusOctroyé
Lodged on20 March 2020date the file was received
Decision notified23 April 202034 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
60 mChange of useRégulariser l'aménagement extérieur et signalétique, mettre en place de nouveau panneaux de signalisation extérieur, mod2024
60 mPublic spaceConstruire un bassin d'orage sous la voirie de Ten Reuken et du parc Axa avec une capacité de 5.171m³.2022
60 mOtherModifier le permis existant du 04/08/2021 2021
60 mOtherPlacer des équipements intérieurs consistant en des installations décoratives et réversibles.2022
60 mOtherModifier le projet dont le PU a été obtenu le 4 août 2021 (réf : 17/PFU/1769123 et son permis modificatif 17/PFU/18116462022

Other nearby cases : 17/PFU/1927334, 17/PFU/1990850, 17/PFU/1933141, 17/PFU/1918639, 17/PU/2002370, 17/PU/1922803, 17/PFU/1846270, 17/PFD/2023287, 17/PU/2020003, 17/PFU/1993476, 17/PFU/2040831, 17/PFD/1929854, 17/PFU/1998123, 17/PFD/1837671, 17/PFD/1994472, 17/PFU/1934277, 17/PFU/1990060, 17/PFD/1950364, 17/PU/1833063, 17/GOU_PU/1901387

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)