Chaussée de La Hulpe 187–189
Watermael-Boitsfort · 17/IPEPLP/1943913 · Prolongation de PE
Chaussée de La Hulpe 187–189, Watermael-Boitsfort: operation of installations. Case octroyé, lodged on 14 May 2024. The decision was notified on 14 May 2025, 365 days after lodging.
Exploitation d'un immeuble de bureaux| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 May 2024 | date the file was received |
| Decision notified | 14 May 2025 | 365 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | New construction | construire un abri à vélos extérieur d’une capacité de 24 emplacements | 2026 |
| 85 m | Tree felling | remplacer une ancienne haie ayant pris trop d'ampleur en abattant 86 arbres haute-tige | 2021 |
| 90 m | New construction | aménager un parking couvert pour vélos | 2022 |
| 90 m | New construction | aménagement d'un parking pour vélo couvert | 2022 |
| 106 m | Tree felling | abattre un tilleul dangereux | 2025 |
Other nearby cases : 17/PU/2003038, 17/PFD/2031005, 17/PU/1801476, 17/PFU/1943228, 17/PFU/1830431, 17/PU/1861333, 17/PFD/1915675, 17/PU/2041152, 17/PU/1940958, 17/PFD/1940128, 17/PU/1899706, 17/PU/1845045, 17/PU/1972435, 17/PU/2040047, 17/PFD/2043867, 17/PU/2023739, 17/PU/1936022, 17/PU/1990821, 17/PU/2015383, 17/PU/1968792
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)