Rue de l'Hospice Communal 182
Watermael-Boitsfort · 17/IPETMP/1945918 · Permis d'environnement temporaire
Rue de l'Hospice Communal 182, Watermael-Boitsfort: operation of installations. Case annulé, lodged on 29 May 2024. The decision was notified on 16 July 2024, 48 days after lodging.
Chantier amiante| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 29 May 2024 | date the file was received |
| Decision notified | 16 July 2024 | 48 days |
| Works started | 21 August 2024 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 7 m | Roof | régulariser la modification de la toiture arrière, la pose d’un auvent au dessus de la terrasse de la cuisine et le remp | 2025 |
| 26 m | Other | régulariser une habitation unifamiliale et réaliser un accès au jardin | 2022 |
| 55 m | Heavy renovation | régulariser des transformations intérieures | 2024 |
| 61 m | Extension or raising | étendre et transformer le rez-de-chaussée et isoler la façade arrière | 2023 |
| 62 m | Heavy renovation | réaménager et rénover une maison unifamiliale avec modification de la toiture de l'annexe et rehausse du mur mitoyen dro | 2022 |
Other nearby cases : 17/PU/2044720, 17/PU/1915793, 17/PU/1828375, 17/PU/2015228, 17/PU/1938608, 17/PU/2015207, 17/PU/1839035, 17/PU/1985478, 17/PFD/1994472, 17/PU/1943096, 17/PFD/1871726, 17/PU/2042002, 17/PU/1822364, 17/PU/1950968, 17/PU/1955070, 17/PU/1835936, 17/PU/1996005, 17/PU/1842787, 17/PU/1832547, 17/PU/1860206, 17/PU/1968513, 17/PU/2044919, 17/PU/2034010, 17/PU/1942247, 17/PFD/1929854
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)