Route de Mont Saint-Jean 2, Watermael-Boitsfort: other. Case octroyé, lodged on 19 April 2000. The decision was notified on 16 August 2002, 849 days after lodging.
modifier une station G.S.M. existante sur un pylône existant| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 April 2000 | date the file was received |
| Consultation committee | 15 June 2000 | |
| Decision notified | 16 August 2002 | 849 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 94 m | New construction | Régulariser la construction d'un pavillon forestier implanté en Forêt de Soignes, et réaliser des travaux de rénovation | 2025 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)