Avenue Delleur, Watermael-Boitsfort: public space. Case octroyé, lodged on 1 December 2003. The decision was notified on 22 July 2004, 234 days after lodging.

construire une sous station de traction pour la ligne 94
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on1 December 2003date the file was received
Consultation committee30 March 2004
Decision notified22 July 2004234 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Consultation committee
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.