Chaussée de La Hulpe 185
Watermael-Boitsfort · 17/PFU/662274 · Permis d'urbanisme unique délivré par le FD
Chaussée de La Hulpe 185, Watermael-Boitsfort: heavy renovation. Case octroyé, lodged on 16 January 2018. The decision was notified on 9 February 2018, 24 days after lodging.
Réaliser des travaux de démontage des cloisons, des faux-plafonds, des revêtements de sol, et évacuation ou mobilier non repris dans la liste établie le 21/12/2017 avec la DMS.
Remplacer 122 vitrages abimés, fendus ou cassés.
| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 January 2018 | date the file was received |
| Decision notified | 9 February 2018 | 24 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Tree felling | remplacer une ancienne haie ayant pris trop d'ampleur en abattant 86 arbres haute-tige | 2021 |
| 20 m | New construction | aménagement d'un parking pour vélo couvert | 2022 |
| 20 m | New construction | aménager un parking couvert pour vélos | 2022 |
| 64 m | — | 17/PU/1801476 | 2021 |
| 64 m | Tree felling | Régulariser l'abattage d'arbres et aménager les abords du bâtiment. | 2022 |
Other nearby cases : 17/PFU/1943228, 17/PU/2044755, 17/AA/2004773, 17/PFD/1915675, 17/PU/1990821, 17/PU/2015383, 17/PFD/1940128, 17/PU/1940958, 17/PU/2003038, 17/PU/1847024, 17/PU/1840059, 17/PU/1871596, 17/PU/2013809, 17/PU/2018554, 17/PFD/1800855, 17/AA/1848544, 17/PFD/2031005, 17/PU/2041152, 17/PU/1861333, 17/PU/1899706
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)