Watermael-Boitsfort · 17/PU/2013859 · Permis d'urbanisme privé
Boulevard du Souverain 88A, Watermael-Boitsfort: roof. Case octroyé, lodged on 17 December 2025. The decision was notified on 6 March 2026, 79 days after lodging.
isoler la toiture de 14 cm| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 December 2025 | date the file was received |
| Decision notified | 6 March 2026 | 79 days |
| Works started | 20 April 2026 | |
| Floor areas | — | not reported by the source |
| Competent authority | Watermael-Boitsfort |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Heavy renovation | transformer le rez-de-jardin et créer une lucarne en façade arrière sur une maison 3 façades unifamiliale | 2026 |
| 12 m | Tree felling | abattre 1 érable dangereux | 2023 |
| 26 m | Tree felling | régulariser l'aménagement de la zone de recul - Article 330 du CoBAT | 2026 |
| 34 m | Extension or raising | transformer et agrandir une maison unifamiliale et réaménager les espaces extérieurs | 2025 |
| 42 m | Extension or raising | régulariser la construction d'un auvent et le remplacement d'une porte de garage | 2024 |
Other nearby cases : 17/PU/2035456, 17/PU/1829017, 17/PU/1970371, 17/GOU_PU/1991676, 17/PU/2026612, 17/PU/1999641, 17/PU/1966812, 17/PU/1997940, 17/PU/2017086, 17/PU/1916311, 17/PU/1922259, 17/PFD/1924327, 17/AA/1924408, 17/PU/1932116, 17/PU/1927337, 17/PU/1996881, 17/PU/1854404, 17/PU/1999600, 17/PU/1855207, 17/PFD/2036905, 17/PU/1952127, 02/PFD/1966156, 17/PU/1833063, 17/PFD/1837671, 17/PFD/1898671
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)