Skip to content
Altaica Urban
Granted

Avenue de Broqueville 169

Woluwe-Saint-Lambert · 18/CL3/1801019 · Déclaration préalable Communal

Avenue de Broqueville 169, Woluwe-Saint-Lambert: operation of installations. Case octroyé, lodged on 23 July 2008.

Transformateur statique
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeDéclaration préalable Communal
StatusOctroyé
Lodged on23 July 2008date the file was received
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
22 mNew constructionrégulariser les travaux effectués (la modification du niveau du jardin, la construction d’un escalier, …) et construire 2026
41 mTree fellingRégularisation de deux arbres abattus par l’ancien propriétaire et demande d’abattage d’un arbre potentiellement dangere2026
72 mChange of userégulariser le placement de plusieurs installations techniques, supprimer un logement pour agrandir le cabinet médical e2023
72 mChange of userégulariser le placement d'une installation technique, modifier l'affectation d'une banque en cabinet médical et placer 2021
99 mSplit into dwellingsrégulariser l'aménagement d'un logement supplémentaire (avec terrasse) dans les combles de l'immeuble2026

Other nearby cases : 18/GOU_PU/1921965, 18/PU/1871196, 18/PU/2016517, 18/PU/1976329, 18/PU/2007715, 18/PU/2012461, 18/PU/1865175, 18/PU/1951200, 18/PU/1843395, 18/PU/1950219, 18/PU/1967842, 18/PU/2034946, 18/PU/2027473, 18/PU/1846464, 18/PU/1838557, 18/PU/2014923, 18/PU/2021323, 18/PU/2007746, 18/PU/1993160, 18/PU/2008117, 18/PU/1960225, 18/PU/1903875, 18/PU/1858687, 18/PU/1870117, 18/PU/2032383

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)