Granted

Avenue Konrad Adenauer 4–8

Woluwe-Saint-Lambert · 18/IPE/465534 · Permis d'environnement

Avenue Konrad Adenauer 4–8, Woluwe-Saint-Lambert: operation of installations. Case octroyé, lodged on 3 May 2012. The decision was notified on 12 November 2012, 193 days after lodging.

Un immeuble comprenant des bureaux et un centre de transfusion sanguine
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on3 May 2012date the file was received
Public inquiry21 June 2012 – 6 July 2012
Decision notified12 November 2012193 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mMerger of dwellingsrégulariser la modification de deux studios (+ mezzanine) en un appartement duplex aux deuxième et troisième étages de l2023
117 mOtherInstaller des cartels - parcours culturel ALlons MArcher !2025
117 mTree fellingabattre quatorze arbres dans le jardin de l'immeuble2022
160 mRetail or horeca fit-outrégulariser la modification de l'utilisation de trois commerces en restaurants (HORECA), les modifications structurelles2021
165 mPublic spaceMaillage bleu UCLouvain - tronçon final : - moine à batardeau (déplacement au Nord de la nouvelle mare - chantier IPI) 2024

Other nearby cases : 18/PFD/1892247, 18/PU/1930406