Skip to content
AltUrb
Granted

Chemin des Deux Maisons

Woluwe-Saint-Lambert · 18/IPE/477295 · Permis d'environnement

Chemin des Deux Maisons, Woluwe-Saint-Lambert: new construction. Case octroyé, lodged on 4 October 2012. The decision was notified on 1 August 2013, 301 days after lodging. It comprises 125 dwellings.

Construction d’un ensemble résidentiel de 125 appartements (A et B)
The application's own description, in its source language (FR). Source: Nova.
125
Dwellings created
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on4 October 2012date the file was received
Decision notified1 August 2013301 days
Works started30 July 2013
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Works started
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
44 mHeavy renovationModifier le permis d'urbanisme 18/PFD/1723972, revoir certaines typologie d'appartement, intégrer des pompes à chaleur, 2026
50 mNew constructionConstruire un immeuble de 83 logements et un parking de 64 places sur 2 niveaux en sous-sol, et aménager les abords2026
91 mFaçade and windowsCLASSE SANS SUITE - placer des tentes solaires ou des screens en façades de l'immeuble2024
91 mFaçade and windowsplacer des tentes solaires, des volets et des screens en façade avant de l'immeuble2025
98 mNew constructionconstruire un immeuble à 64 appartements « Flora » et 45 (+4) parkings couverts et abattre 30 arbres2021

Other nearby cases : 18/GOU_PU/1894055, 18/PU/1961775, 18/PU/1986984, 18/PU/2008051, 18/PU/1954199, 18/GOU_PU/1930658, 18/PFD/1911332, 18/PFD/1953562, 18/PU/1908274, 18/PU/1826837, 18/PU/1946135, 18/SFD/1974495, 18/PU/1979768, 18/PU/1958961

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)