Skip to content
AltUrb
Granted

Kerkedelle 27–37

Woluwe-Saint-Lambert · 18/IPE/480801 · Permis d'environnement

Kerkedelle 27–37, Woluwe-Saint-Lambert: —. Case octroyé, lodged on 19 December 2012. The decision was notified on 4 July 2013, 197 days after lodging.

Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on19 December 2012date the file was received
Decision notified4 July 2013197 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
16 mFaçade and windowsisoler et enduire le mur pignon de l'immeuble2023
19 mRoofisoler les façades, le pignon, la lucarne existante à l'avant et la toiture, régulariser la largeur de la lucarne exista2025
31 mFaçade and windowsRénovation d'une maison unifamiliale mitoyenne (isolation des façades)2026
37 mExtension or raisingrégulariser la modification de la véranda à l'arrière de la maison unifamiliale2021
37 mFaçade and windowsrégulariser les modifications apportées à la maison unifamiliale (menuiseries extérieures, baies intérieures, ...)2021

Other nearby cases : 18/SFD/1828909, 18/PU/1966206, 18/PU/2011270, 18/PU/1989687, 18/PU/1822726, 18/PU/1974055, 18/PU/1912885, 18/PU/1892347, 18/PU/1909264, 18/PFD/2009080, 18/PU/1997195, 18/PU/1904155, 18/PU/2035016, 18/PU/2034864, 18/PU/2001774, 18/PFD/1933805, 18/PFD/1857608, 18/PU/2020829, 18/PFU/1830434, 18/PU/1956995, 18/PU/1924319, 18/PU/2003922, 18/PU/1968408, 18/PU/1832560, 18/PFD/1968760

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)