Skip to content
Altaica Urban
Granted

Boulevard de la Woluwe 64

Woluwe-Saint-Lambert · 18/IPE/621852 · Permis d'environnement

Boulevard de la Woluwe 64, Woluwe-Saint-Lambert: —. Case octroyé, lodged on 14 December 2016. The decision was notified on 3 January 2018, 385 days after lodging.

Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on14 December 2016date the file was received
Public inquiry18 April 2019 – 3 May 2019
Consultation committee28 June 2019
Decision notified3 January 2018385 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Public inquiry opened
  6. Public inquiry closed
  7. Consultation committee

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mSigns and advertisingCLASSE SANS SUITE placer un totem dans la zone de recul de l'immeuble2024
0 mSigns and advertisingplacer un totem en zone de recul de l'immeuble2025
44 mPublic spaceRéaménager le parc Saint-Lambert.2022
49 mPublic spaceRéaménager le parc Saint Lambert avec une installation artistique qui soulignera le caractère naturel du site.2024
52 mDemolition and reconstructionDémolir l’immeuble de bureaux, à l’exception de la structure périphérique du sous-sol, et construire un nouvel immeuble 2023

Other nearby cases : 18/PFD/2037541, 18/PFD/2009080, 18/PU/1997195, 18/PU/2001774, 18/PU/1912885, 18/PU/2035016, 18/PU/1825278, 18/PU/1825288, 18/PU/1966206, 18/PU/1989687, 18/PU/1892347, 18/PU/1902328, 18/PU/2018121, 18/PU/2026548, 18/PU/1973486, 18/PU/2044356, 18/PU/2011270, 18/PFU/1998458, 18/PFU/2022965, 18/PFU/1991105, 18/PFU/1952749, 18/PFU/1914471, 18/PFU/1859699, 18/PFU/1830434, 18/PFU/1950704

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)