Chaussée de Stockel 243–257
Woluwe-Saint-Lambert · 18/IPEEXT/496345 · Extension / Transformation de PE
Chaussée de Stockel 243–257, Woluwe-Saint-Lambert: operation of installations. Case octroyé, lodged on 13 January 2014. The decision was notified on 3 February 2014, 21 days after lodging.
Plans modifiés suite à l'application de l'article 126/1 du COBAT dans le cadre du permis d'urbanisme| Permit type | Extension / Transformation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 13 January 2014 | date the file was received |
| Decision notified | 3 February 2014 | 21 days |
| Works started | 3 September 2014 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 46 m | Energy works | placer une centrale de cogénération dans l'immeuble | 2021 |
| 84 m | Change of use | régulariser les travaux effectués, diviser la maison unifamiliale en deux entités (cabinet médical et logement), isoler | 2023 |
| 102 m | Tree felling | Abattre 57 arbres | 2023 |
| 102 m | Tree felling | Abattre 57 arbres | 2022 |
| 122 m | Tree felling | Abattre 11 arbres à hautes tiges et un plan de replantation est prévu, avec des arbres et arbustes indigènes. | 2021 |
Other nearby cases : 18/PFD/1994969, 18/PU/1989945, 18/PFD/1892684, 18/PU/1967845, 18/PU/1983687, 18/PU/1834887, 18/ECO/1934072, 18/PFD/1934327, 18/PFD/1799210, 18/PU/1898720, 18/PFU/2018620, 18/PU/1898306, 18/GOU_PU/1989916, 18/PU/1988652, 18/PU/2022604, 18/PU/1969670, 18/PU/2035409, 18/PFD/1907937, 18/PFD/1921707, 18/PU/1935456, 18/PU/1899692, 18/PU/2044415, 18/PFD/1853237, 18/PU/1856996, 18/GOU_PU/1938783
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)